Industrial facilities

Wastewater Treatment Plant in Minsk Mazowiecki

Date of implementation:
11.2020 - 03.2023
photo of Wastewater Treatment Plant in Minsk Mazowiecki

Comprehensive execution and modernization of electrical installations, including complete modernization of the power supply system of the treatment plant with the supply of transformer MV switchgear and modernization of existing MV overhead line poles.

Project summary:
Type of project:
Industrial facilities
Place of implementation:
Mińsk Mazowiecki
Date of implementation:
11.2020 - 03.2023
Type of works:
Electrical installations
By subscribing you agree to with our Privacy Policy.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Share
What's new?

News and Challenges

Our improvements and the need for continuous accessibility in the engineering world

Stay tuned as we improve the

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Career

Your path to professional development

Create your own career path in electrical industry. Check out our latest job offers and join our team.

read more
more